Since 1 January 2026 importers of steel, aluminium, cement, fertilisers, hydrogen and electricity pay for the emissions embedded in those goods, at the same price EU producers pay under the EU ETS.
Who pays
The EU importer, through CBAM certificates. The price follows EU ETS auctions.
Whose data counts
The producer's. Emissions are measured at the installation outside the EU, per product and production route.
What if data is missing
Default values set by the Commission apply. They are designed to be higher than good actual data.
The dates that matter
The transitional period was reporting only. From 2026 CBAM costs money.
Definitive period
Importers become liable for embedded emissions.
Authorisation
Importers who applied by this date may keep importing while the decision is pending.
Certificate sales
CBAM certificates go on sale, covering 2026 imports.
First declaration
Annual declaration for 2026 imports is due.
Downstream goods
About 180 products made with steel and aluminium may be added.
Proposal
Free allocation ends
EU free allowances phase out; the CBAM charge rises in step.
Two sides, one data chain
Producers supply the data. Importers pay the bill.
CBAM only works when emissions data flows from the factory to the EU buyer. CO₂ Manager handles both ends.
Producers and exporters outside the EU
Keep your EU customers
Calculate embedded emissions per installation, route and product
Send your buyers the Commission's communication template
Show carbon prices already paid at home, such as a national ETS
Covers clinker and cement. Here indirect emissions from electricity count too.
CN headings6
Emissions countedDirect and indirect
50 t thresholdApplies
Main precursorClinker
01In plain words
Cement gets its strength from clinker, made by heating limestone and clay to about 1,450 °C. Heating needs fuel, and the limestone itself releases CO₂ when it breaks down. Because cement plants also use a lot of power, CBAM counts the electricity too.
02How it is made, and where the CO₂ comes from
Quarry
Limestone and clay are extracted and ground
Kiln
Raw meal is burned into clinker; fuel and limestone release CO₂
Clinker
The main precursor; can be sold to other plants
Grinding
Clinker is ground with gypsum and other materials
Cement
Bagged or bulk cement shipped to customers
Fuel burnedProcess emissionsElectricityPrecursors bought in
Coloured dots show where emissions arise at each step.
03How CBAM works for this product
Producer
Measure at the plant
The producer monitors fuels, materials and output at each installation.
Producer → buyer
Share with the buyer
Embedded emissions per product go to the EU buyer in the Commission's template.
EU importer
Declare and pay
The EU importer declares the imports and surrenders CBAM certificates.
Verifier
Verify
An accredited verifier checks the actual emissions data.
04Covered CN codes
CN code
Goods
2507 00 80
Other kaolinic clays, calcined
2523 10
Cement clinker
2523 21
White Portland cement
2523 29
Other Portland cement
2523 30
Aluminous cement
2523 90
Other hydraulic cements
Not covered: uncalcined kaolin and clays, concrete and concrete products.
05Emissions, routes and precursors
Emissions counted
Direct and indirect emissions. Electricity used in production counts.
Routes
Clinker production in rotary kilns: dry, semi-dry, wet
Cement grinding and blending
Calcination of clay
Precursors
Clinker and calcined clay bought from other installations.
06What to watch
The clinker ratio largely sets the embedded emissions of the cement.
Process emissions from calcination are large and must be monitored apart from fuel emissions.
For indirect emissions a grid factor applies unless actual values can be justified, for example by a direct line or power purchase agreement.
Alternative fuels and biomass need proper evidence to be counted correctly.
Grinding plants that buy clinker need their clinker supplier's data.
07What your EU buyer will ask for
Installation name, location and production routes
Fuel and material inputs with emission factors
Production quantity per CBAM good
Precursors bought, with their embedded emissions
Electricity consumed and its source
Carbon price paid in the country of origin, if any
08Key terms
Clinker
Hard nodules from the kiln; the active ingredient of cement.
Calcination
Limestone splitting into lime and CO₂ when heated.
Clinker ratio
Share of clinker in the cement: lower ratio, lower emissions.
Indirect emissions
Emissions from producing the electricity a plant uses.
09Common questions
Is ready-mix concrete covered?
No. Concrete and concrete products are not in scope; cement and clinker are.
Why does electricity count here but not for steel?
In the definitive period indirect emissions count for cement and fertilisers; for steel, aluminium and hydrogen only direct emissions count.