Since 1 January 2026 importers of steel, aluminium, cement, fertilisers, hydrogen and electricity pay for the emissions embedded in those goods, at the same price EU producers pay under the EU ETS.
Who pays
The EU importer, through CBAM certificates. The price follows EU ETS auctions.
Whose data counts
The producer's. Emissions are measured at the installation outside the EU, per product and production route.
What if data is missing
Default values set by the Commission apply. They are designed to be higher than good actual data.
The dates that matter
The transitional period was reporting only. From 2026 CBAM costs money.
Definitive period
Importers become liable for embedded emissions.
Authorisation
Importers who applied by this date may keep importing while the decision is pending.
Certificate sales
CBAM certificates go on sale, covering 2026 imports.
First declaration
Annual declaration for 2026 imports is due.
Downstream goods
About 180 products made with steel and aluminium may be added.
Proposal
Free allocation ends
EU free allowances phase out; the CBAM charge rises in step.
Two sides, one data chain
Producers supply the data. Importers pay the bill.
CBAM only works when emissions data flows from the factory to the EU buyer. CO₂ Manager handles both ends.
Producers and exporters outside the EU
Keep your EU customers
Calculate embedded emissions per installation, route and product
Send your buyers the Commission's communication template
Show carbon prices already paid at home, such as a national ETS
Covers electricity imported into the EU through interconnectors. Special rules apply.
CN headings1
Emissions countedGeneration
50 t thresholdDoes not apply
Main precursorNone
01In plain words
Electricity crosses borders through power lines called interconnectors. CBAM puts a carbon price on electricity imported into the EU, based on how much CO₂ the power plants of the exporting country or region emit.
02How it is made, and where the CO₂ comes from
Power plant
Coal, gas, hydro, wind or solar
National grid
Power flows into the transmission grid
Interconnector
Cross-border line into the EU
EU grid
The importer declares the imported electricity
Fuel burnedProcess emissionsElectricityPrecursors bought in
Coloured dots show where emissions arise at each step.
03How CBAM works for this product
Producer
Measure at the plant
The producer monitors fuels, materials and output at each installation.
Producer → buyer
Share with the buyer
Embedded emissions per product go to the EU buyer in the Commission's template.
EU importer
Declare and pay
The EU importer declares the imports and surrenders CBAM certificates.
Verifier
Verify
An accredited verifier checks the actual emissions data.
04Covered CN codes
CN code
Goods
2716 00 00
Electrical energy
05Emissions, routes and precursors
Emissions counted
Emissions from generation. Default factors for the exporting country or region apply unless strict conditions for actual values are met.
Routes
Grid imports through interconnectors
Imports from a named installation with a power purchase agreement
Precursors
None.
06What to watch
No 50 t threshold: the obligation applies from the first import.
Actual emissions can only be used with a clear link between the generating installation and the import, including a firm capacity nomination.
Default values reflect the grid of the exporting country or region.
Mostly relevant for neighbouring countries with interconnectors to the EU, such as Türkiye, the Western Balkans and Ukraine.
07What your EU buyer will ask for
Installation name, location and production routes
Fuel and material inputs with emission factors
Production quantity per CBAM good
Precursors bought, with their embedded emissions
Electricity consumed and its source
Carbon price paid in the country of origin, if any
08Key terms
Interconnector
A power line linking two national grids.
Grid emission factor
Average CO₂ per MWh of a country's power system.
PPA
Power purchase agreement with a named power plant.
09Common questions
Can renewable power avoid the default value?
Only under strict conditions, including a direct link to the plant and a firm capacity nomination for the import.